koefitsient mis iseloomustab ajakavast kinnipidamist, efektiivsust, teenitud väärtuse ja planeeritud panuse suhe
an indicator of project schedule efficiency
a measure of schedule efficiency expressed as the ratio of earned value to planned value
Это интересно
Kui see näitaja on vähem kui 100 %, tähendab see mahajäämust ajakavast; kui see on rohkem kui 100 %, tähendab see ajakavast ees olemist
Это интересно
t is the ratio (percentage) of the earned value (progress) and the planned effort (Ratio= Progress/Planned effort/ *100). If this indicator is less than 100 % it means that the project is behind schedule; if it is higher than 100 % it means that the project is ahead of schedule